Obtained arbitration ruling in favor of a general contractor that a release that it executed during the construction of a state transportation facility only barred those claims of the general contractor and its subcontractors that existed or that could have been brought prior to the execution of the release, which led to a settlement of $500K in favor of the general contractor.